Thermal Power Station 210 MW

Thermal Power Station


Introduction:-

              

Thermal power plant comprises of the 210 MW, The equipments for the 210 MW turbogenrators are supplied by BHEL and Boiler is corner fired, incorporate with American design made by combustion engineering. The turbines are of Russian design has been considered for case study. Each unit has individual Control room.

Case study considering the 210MW Station of 4 units, after Commissioning of all four units the total installed capacity of the plant is 840MW. Total area of power station is 1733 Acres.

Total coal requirement per day is 4000T

2. PRINCIPLES of power generation:-

             According to the law of conservation of energy,” Energy can neither be created nor be destroyed but it can be converted from one form to another form the total energy in the universe remains constant”.

              In thermal generation with boilers, coal is ground to a powdered form in coal mills and blown it into a furnace along with a stream of primary air. In the furnaces, the fine coal particle burnt in suspension thus converting the chemical energy of coal into heat energy. This heat energy converted into a steam having high pressure & temperature heats up denaturalized water tubes’ surrounding the furnaces. This superheated steam is led to the turbine where heat energy of steam utilized as it rushes past the rotor blade to drive the generator and producing electricity.

              After it passes through the turbine the relatively cool steam at low pressures passed on to the condenser where it is condensed into a water and is pumped back to the boiler drum as water passes to the boiler it is heated in feed water heater to increase the efficiency of plant.     

                                                             


                                                    GENERAL LAYOUT

  

Different Departments of Thermal power plant:-

3.1. introDUCTION: -

            Requirement of coal for such a big power plant is enormous TPS required 4 MT of coal per day.

3.2. COAL HANDLING PLANT: -

            This plant handles the coal from its receipt to transporting it to boiler and store in bunkers. It also processed the raw coal to make It suitable for boiler operation. Basically CHP consist of hopper for receiving coal from front-end loaders or dumpers. A grating is provided above the hoppers, which limit maximum size of coal going to conveyor belt. A vibro-feeder that controls the flow of hopper to belt conveyor & carries it to crusher or a vibrating screen depending upon the size of raw coal.

                It should also be ensure that no metallic particle get mixed with coal & gas to the crushers that would reduce the crushers’ life to the great extent.

            Now a day’s metal detector electromagnet separator can be used for removing metallic item from coal. The crushers should also ensure that correct size particles go to the boiler bunker higher size and fine want escape without getting burnt. The crushers and screen is the hurt of CHP & should be chosen with almost care with due consultation with specialist. In India Bevin ways specializes in CHP.

Receipt of coal: - Normally Thermal Power Plant receives the coal by    

Three modes of transportation

1)   By Railway: -The 80 to 90% of requirement coal is fulfill by this way.

2)   By Road: -The 10 to 20 % of requirement coal is fulfill by this way.

3)   By Ropeways: - Not available

           Cost of the road transportation is higher than that for rail & hence most of the coal requirement is fulfill by Railway transport and also major auxiliary.

MAJOR AUXILIARY OF CHP: -

Wagon tippler

Vibrating feeders

Conveyor belt

Trippers

Electromagnetic separator

Dust extraction system

               One wagon contains 66 tons of coal. Which are unloaded to coal hoppers in very less time by using wagon tipplers which works on speed of 20wagons/hours

                After that 80 mm coal is crushed in primary crusher to 60mm size. After that it is passed through secondary crusher where it is again crush to a size of 20mm and then it carry through a conveyor belt to hoppers where it is again crushed to very small size and given to coal mills where it is converted into fine size powdered form and fired in boiler furnace.

 

STACKING OF COAL: -

              Commencing with the adequate preparation of the site or coal, stoke pills. Having regarded to environmental protection requirement drainage and stability of stoke pills must precede the instant of coal stoking and reclaiming machineries.

3.3 OIL HANDLING PLANT: -

             Oil is used as a secondary fuel for the boiler and is required for initial startup and low load operation period. Fuel oil is received in rail tanker. The power plant has unloading capacity of 64 rail tankers at a time.

 WATER TREATMENT PLANT: -


       For the unit operating at high pressure and temperature, extremely pure water is require to prevent corrosion, erosion, scaling. Such water requirement meets by dematerialized plant having capacity of 550 MT/hr. Also to cater for the need of cooling water for condenser, oil coolers etc. The water is supplied by softened water plant having capacity of 6000 MT/hr. Before admitting to the treatment plant the water the river water is clean in carificulator and the gravity filter.

3.5 DEMINRALIZATION: -

              It is a process of removing ionisable solids from the water using principles of ion exchange. In a softener, the ion exchange process is relatively simple and consists essentially of exchange the minerals calcium and magnetism for the demineralized in terms of the water quality they produce.

              The two column deionizer yields water of about 10 PPM TDS specific resistivity of about 25000 ohms/cm. Mixed bed demineralized yield water with less than 1 PPM TDS and up to 18300000 ohms/cm specific resistivity it should be pointed out demineralized remove ionisable solids and resin will remove CO2 chemically it may be more economical to remove it without a mechanical degasify specially when large CO2 is involved. Cation used to remove to use to positive radicals and Anion used to remove the negative radicals.

4 Boiler and Accessories:-

4.1 INTRODUCTION:-

                    Boiler is a heart of power plant in mechanical point of view. Basically boiler is a closed vessel in which steam is produced from water by combustion of fuel. Input of boiler is generally coal, oil, water, air i.e. Chemical energy is converted in to heat energy and output of a boiler is flue gas, ash, steam. Heat is transferred in boiler by conduction, convection and radiation.

 


COMBUSTION THEORY: -                     

        Combustion is a chemical reaction in between combustible and oxygen in air, which releases heat, where combustible substance such as carbon, hydrogen, sulphar, etc. oxidizing combustion process. In practice if fuel is burnt with only the theoretical amount of air present then the combustion will be very poor due to incomplete with air.

4.2 TYPES OF BOILER: -                        

Depends upon the pressure boilers are classified as:

·                   Industrial boiler: - for less pressure up to 60 kg/cm2 and Temperature up to 350°C

·                   Utility boiler: - high pressure and high temperature and                            generally used in power generation.

·                   Single drum (sub critical boiler)

·                   Superheated boiler (forced circulation)

 

4.3 TYPES OF DRAUGHT: -

i) Natural draught        : - It is created by using height of chimney

ii) Forced draught        : - It is created in furnaces by F.D. fan

iii) Induced draught     : - It is used to evacuated the flue gases with the                                    help of I.D. Fan

iv) Balance draught     : - Balance draught is the combination of forced    as well as Induced draught.

     

                                                            Boiler Furnace

4.4 BOILER FURNANCE: -

           Boiler furnaces are sized to ensure complete combustion of fuel. The furnaces are enclosed with water wall made of Tubes in welded wall construction connected with headers of top and Bottom. The design and construction of furnaces is such that it will prevent distortion of steel work due to thermal expansion and deterioration of insulation.

          The entire furnaces structure is suitable supporting Structure to allow free expansion of surface.

4.5 BOILER ACCESSORIES: -

1)   ECONOMISER: -

            Purpose of economiser is to preheat the boiler feed water and recovers the heat from flue gasses. Economiser is located in boiler second pass below low temperature Superheater coil. The feed water flows in upward direction through the economizer that is counter flow to flue gasses ensuring heat transfer.    

 

2)   SUPERHEATER: -

It is composed of four basic stages; a pendant section, a platen section, rear horizontal section and steam cooled valve section and roof section. Platen section is located directly above the furnace in front of the furnace. Superheater consisting of 14 sections the horizontal section of superheater is located in rear vertical gas pass above the economiser, this primary superheater of convictive counter flow type.

3)   REHEATER: -

it is composed of two stages front and rear section. The front section is located between rear water wall hanger tubes and superheater platen coils. The rear section is located between water-cooled screen tubes and rear water wall hangers tubes. Function of reheater is to reheat the steam, and then it’s expansion in HP turbine. This material is having the property of resistance to erosion and high temp. Creep resistance.

4)   DESUPERHEATER: -

This is provided with superheater connecting link and CRH line, it is provided to control the temperature of steam in the circuit.

5)   SOOT BLOWER: -


It is necessary to remove the deposits, which is settled on tube, this reduces the heat transfer rate of the tubes.

          Types of soot blower are:

                     a) Wall blowers

                     b) LRSB (Long retractable soot blower)

 

6)   BOILER DRUM: -

It is located above the furnace which eliminates necessity of providing pump for the circulation of feed water in water valve. Main function of boiler drum is separation of moisture content from the steam. here separation will take place in two stages in turbo separator and saturated steam leads to turbine via various stages of SH.

           

4.6 BOILER SPECIFICATION: -

Manufacturer                         :  BHEL, C.E DESIGN

Type                                       :  natural circulation, balance draught, double                                   pass Single drum, single reheat.

Boiler pressure & temp.        :  182KPa, 540°C

Type of firing                        :  tangential corner fired.

Furnace width                        :  13.868M

Furnace depth                        :  10.59M

Furnace plane area                :  147sq.M

Furnace volume                    :  5200sq.M

Height                                     :  51 M

 

5. ASH HANDLING PLANT:-

         The ever increasing capacities of boiler units together with their abilities to use low grade high ash content coal have been responsible for the development of modern day ash handling systems. the widely used ash handling systems are;

1) Mechanical Handling System

2) Hydraulic System

3) Pneumatic System

4) Steam Jet System

             The hydraulic ash handling system is used at Colombia power plant.

HYDRAULIC SYSTEM: -

          The hydraulic system carried the ash with the flow of water with high velocity through a channel and finally dumps into a sump. the hydraulic system is divided into a low velocity and high velocity system. In low velocity system ashes from boilers are fall into stream f water flowing into the sump. The ash is carried along with the water and they are separated at the sump. in the high velocity system the jet of water is sprayed to quench the hot ash. the advantage of the system are that its clean, large ash handling capacity, considerable distance can be traversed, absence of working parts in contact with ash.

 ASH COLLECTION: -

BOTTOM ASH COLLECTIONS AND DISPOSAL: -

        At the bottom of the furnace there is a hopper for collection of bottom ash. This hopper is always filled with water to quench the ash and clinkers falling down from the furnace. Some arrangements are included to crush the clinkers and bottom ash to storage site.

FLY ASH COLLECTION: -

        Fly ash is captured and removed from the flue gas by electrostatic precipitator located at the outlet of furnace and before the induced draught fan. The fly ash is periodically removed from the collection hoppers below the ESP. generally; the fly ash is pneumatically transported to storage silos for subsequent transport by truck or railway.

5.3 ELECTROSTATIC PRECIPITATOR: -

 

 

Basic Functions of ESP: -

1) Removes fly ash from flue gasses.

2) They can collect particles sized 0.1-10 microns very efficiently

3) They are generally more efficient at collecting fine particles than scrubbers. OR cyclones.

4) ESP’s can handle hot gasses from 350 to 1300 degree Fahrenheit.

BASIC PRINCIPLE OF OPERATION: -

1) Ionization-charging of particles.

2) Migration-transporting the charge particles to the collecting surfaces.

3) Collection-precipitation of the. Charge particles onto the collecting surface.

4) Charge dissipation neutralizing the charge particles on collecting surface.

5) Particle removal-conveying the particle from the hopper to a disposal point.

5.4 MAINTENANCE OF ESP: -

1)   Do not disturb the guide vanes, splitters, and deflectors plates on the gas distribution screen or the internal alignments during the inspection to maintenance.

2)   Every available shut down may be utilized to remove the excessive ash built up if any.

3)   All the internal casing hoppers and roof shall be inspected for corrosion/erosion/wear and tear/leakage periodically.

4)   The asbestos ropes and gaskets shall be replaced whenever required to prevent ingress of air into ESP.

5.5 SCOPE FOR IMPROVEMENT: -

1) ESP water washing option is to be discussed to improve its performance.

2) ESP rapping should be made on continuously after every unit shutdown.

3) GD test to be done for checking of uniform flow of flue gas.

4) Ammonia dosing system to be run continuously.

5) Water fogging system at ESP inlet.

   

6. TURBINE: -

            The turbine is condensing, tandem compound, 3 cylinders, horizontal, disc and diaphragm type with nozzle governing and regenerative feed water heating. The double flow LP turbine incorporates multi exhaust in each flow.         

             Steam at a temperature of 540°C and a pressure of about 140 KPa is let out from the boiler and admitted into the turbine where its heat energy is converted into mechanical energy. The steam after passing through HP cylinders is again passing on the boiler for superheating to a temp. Of 540° C. This reheated steam is later admitted into IP and LP turbine stages to extract more heat energy and then condensed in the condenser to form the water. The turbine shaft drives the rigidly connected rotor of the generator to produce electricity.

            The turbine hall of stage 2 is huge structure measuring 41.5M in width and 19M in height and 210M in length.

6.1. HP, IP AND LP TURBINE: -

           The high-pressure turbine (HPT) comprises of 12 stages, the first stage being governing stage. The steam flow in HPT being in reversed direction, the blades in HPT are design for anticlockwise direction, when viewed in the direction of steam flow. After passing through HP turbine steam flows to boiler for reheating and reheated steam comes to IPT through 2 interceptor wall and four control valves mounted on IPT.

       The intermediate pressure turbine has 11 stages. HP and IP rotors are connected by rigid coupling and have a common bearing. After flowing through IPT, steam enters the middle part of LPT through 2 crosses over pipes.

       In LPT, steam flows in opposite paths having 4 stages in each path. After leaving the LP turbine the exhaust steam condenses in the surface condensers welded directly to the exhaust part of LPT.

       The turbine is equipped with a barring gear which rotates the rotor of turbine at a speed of nearly 3.4 rpm for providing uniform heating during starting and uniform cooling during shut down.

6.2. TURBINE BEARINGS: -

The 3 turbine rotors are supported on 5 bearings. But 2 most important types are: -

1)   Thrust bearing: -

                This bearing is of Mitchell type with the bearing surface distributed over the no. of bearing pads lined with white metal. They are pivoted in housing on the side of a rotor thrust collar. During operation an oil film is formed between pads and thrust collar and there is no metal-to-metal contact.

2)   Journal bearing: -       

            The journal bearing nos.1, 3, 5, 4, consist of outer shell of cast iron with n inner shell line with white metal. Both the shells are split at half joint and secure by bolts.

 

6.3. turbine specifications: -

Rated o/p of turbine                       : 210 MW 

Rated speed                                      : 3000rpm

Rated pressure of                            : 130 KPa

steam before ESV

Steam flow at 210 MW                  : 652 t/hr

Rated C.W. inlet temp.                   : 30°C

Rated C.W flow through

Condenser                                       : 27000m3/hr

Rated efficiency of turbine            : 42.5%

Stages of turbine                             : 12,11,8

No. of bearing                                 : 5

Condenser specification                 : 14600m2, 2 pass, 15620 tubes, 30 mm                                                       dia. 10 m long.

Length of longest LP blade            : 765 mm

Operating governing oil  pressure: 20 KPa

Capacity of HP, LP bypass

System                                             : 30%

Main lubricating oil tank capacity: 28000ltr.

Specification of oil used                : turbine 14, sp.gr. 0.852

 

7. GenRaTOR:-

7.1 GENERAL: -

           Modern features of direct cooling by water and hydrogen are incorporated with the 210MW turbo generator, thus evolving an economical and reliable design. The machine is provided with fast acting excitation system and dependable aux. service to give prolonged trouble free operation over the years.

STATOR BODY:

         The stator body is totally enclosed, has tight fabricated structure, suitably ripped internally to ensure high rigidity. It is design mechanically to withstand internal pressure on explosion of hydrogen air mixture without any residual deformation. Hydrogen gas coolers are housed longitudinally inside the stator body.

STATOR CORE:

        Stator core is made up of segmental, varnish insulated punching of cold rolled grain oriented silicon steel assembled in an inter repaved manner on core bars. The core is made u of several pockets separated by steel spares for redial cooling of the core by hydrogen. In order to isolate the stator body and this foundation from magnetic vibration of stator cores, thus core bars are design to provide elastic suspension of the core in the stator.

STATOR WINDING AND INSULATION:

          The stator has three phase double layer short chorded bar type windings have two parallel paths. Each coil side consists of glass insulated solid and hollow conductors with cooling water passing through the later. Adequate protection is provided to avoid coronas and other surface discharges.

TERMINAL BUSHINGS:

       Water-cooled terminal bushings are housed in the lower part of stator on the slip ring inside. Porcelain insulators are provided to insulate the terminal bars from the stator body. Terminal bushings can be replaced without removing the stator from foundation.

ROTOR: 

        The rotor is of cylindrical type, shaft and body being forged in one piece from chromium, nickel, and molybdenum, vanadium steel.

The rotor with all the detail assembled is dynamically balanced to a high degree of accuracy and subjected to 20% of over speeding for 2 min. ensuring mechanical strength. Cross sectional view of assembled rotor is given.

FIELD WINDING:

        The field winding is made from hard drawn silver bearing copper. Rotor winding is held in position against centrifugal forces by duralium wedges in the slot portion and by non magnetic steel retaining steel in the overhead portion. The rotor slot wedges are of special profile with elliptical holes milled into match the ventilation ducts on the winding stacks.

         Copper segmental type damper winding is provided in the end zone of rotor in order to prevent over heating of retaining rings during asymmetrical and asynchronous operations.

 

SLIP RINGS:

         The slip ring consists of helically grooved alloy steel rings shrunk on the rotor shaft and insulated from it. For convenience in assembly both the rings are mounted on single, common steel bush, which has an insulating jacket pre-mounted on it. And complete bush with slip rings is shrunk on the rotor shaft.

7.2 TECHNICAL SPECIFICATIONS OF 210 MW

GENERATORS 

Max. KVA rating                            :  247000 KVA

Max. KW rating                              :  210000 KW

Rated terminal voltage                   :  15.75 KV

Rated stator current                        :  9050 Amp

Rated power factor                         :  0.85 lag.

Excitation current                           :  2600 Amp

Rated speed                                     :  3000 rpm

Rated freq.                                       :  50 Hz

Phase connection                            :  double star

No. of terminals                     :  9 (6 for neutral and 3 for phase)

Class of insulation                          :  “B”

Type of cooling                              :  Hydrogen cooling for Rotor &

                                                         Water-cooling for Stator.

 8. TRANSFORMER: -

             Transformers are the heart of electrical power system because without transformer there is no step up and step down of electrical power, hence there are various causes are produced like voltage drop and there is not transmission and distribution of electrical power is possible. In a power station the transformer is used for a stepping up the output voltage of an alternator for further transmission of electrical power. In a power station there are mainly three types of transformer are used unit auxiliary transformer, station transformer, and main output transformer.          

              The unit auxiliary transformer are used for supplying the load to various auxiliary of power station at voltage of 6.6 kv which is step down at 15.7/6.6 kv, such as boiler feed pump, condensate extraction pump, Induced draught fan, forced draught fan etc. and there is also having a low voltage auxiliary for the voltage of 440 v such as various types of ac motors used for pumping the water, and the motors are also used in water treatment plant and DM plant.

              The station transformers are used when the whole units are shut down and we must require starting the plant, the station transformer collects the supply from grid and gives the supply to the auxiliary of a power plant.

              In stage two of power plant output of the generator is 15.75 KV, which is transferred to both transformers through oil ducts. The unit auxiliary transformer of stage two is stepping down the voltage at 15.75/6.6 KV and the transformer, which is the generator transformer step-ups, the voltage at 15.75/220 KV.