Installation, Testing, Commissioning, Operation & Maintenance of Electrical Power Equipment's

Installation, Testing, Commissioning, Operation & Maintenance of Electrical Power Equipment's

                                                                                                        

1.0       Introduction       :         

 

1.1       Role of Electrical Energy : Major Portion of the electrical energy is generated to meet the demand of large industrial units, small industries, agriculture & domestic sector gets a small portion. Electrical energy is clean, congenial & pollution free. It increases the production & improves the quality of manufactured goods and at optimal, economical & competitive prices for the consumers & manufacturers.

 

1.2       Electrical Hazards & Safety:   It is very safe to use the electrical energy. With careless hands, it may cause fire, accidents & hazards. To ensure the safe use of electrical energy, it is important to select the correct electrical power equipments, install & commission the same in a systematic way. The equipment should be of good quality materials, proper wiring & protective devices be provided during their installation & commissioning. It should be followed by effective maintenance & upkeep of protective devices. These could be achieved by strictly observing electricity safety rules & codes, regulations & to follow maintenance schedules regularly..

 

1.3       Importance of Competency: For the safe use of electrical equipments & installations, it is the need to have competent electrical engineers, supervisors & trained workers. They should have sufficient knowledge & experience to operate & maintain the electrical equipments with reasonable care, efficiency & safety.

 

1.4       Installation:  The electrical equipments are to be placed to do the specific job. The process of installing equipment is called installation. Depending upon the size of the equipment, the schedules of installation are prepared & accordingly it is installed. For e.g. to install a generator of large capacity it requires sound foundation structure, good fittings, overhead cranes & special tools for proper erection & fittings of various parts. Before installation, it is also necessary to carry out the specific tests at the premises of the supplier. If those inspections & tests are ok, then the various parts are transported to the site of installation. The generator is installed on foundation, checked for various clearances & alignment & other mechanical checks, so that it works properly with the coupled prime mover. After satisfactory installation, pre commissioning checks & tests are made. When the checks & tests are ok, then it is commissioned & put in to commercial operation.

 

1.5       Supervisor    : An electrical engineering technician should have sufficient knowledge of the equipment so as to inspect, test & certify the work done by the skilled workers. To effectively perform his duty, he must demonstrate the correct method & procedures to do the various operations, possess manual skills & has conceptual understanding.

 1.6       Maintenance Executive:   The success of an installation depends upon the executive in charge of its maintenance department. He should ensure satisfactory operation of all equipments and safety of personnel. Efforts should be made to prevent breakdowns, which cause serious losses, difficulties in management besides losing production. He is not only be technically sound but must be a psychrist to ensure the co operative attitude of the workers.

 1.7       Preventive Maintenance:   Preventive maintenance ( P M) methods should be adopted to reduce loss of production, which results in profitability through equipment out put & running cost. To achieve this, it is essential to organize the maintenance of different sections on scientific terms. P M is the most appropriate answer to these requirements & should be based on regular scheduled inspections, minimize breakdowns, prevents safety hazards & depreciation of the plant & equipment.

             As the major objective of P M is contribution of profitability, it can be achieved by the following:

a)      By reducing production down time

b)      By increasing life expectancy of machines.

c)      By economical use of maintenance workers,

d)     By routine repairs to replace large-scale repairs.

e)      By repairing before failure to reduce cost.

f)       By identification of equipment with excessive cost

g)      By improved safety

 

Establishing of a P M could be achieved by preliminary planning, Preparing machinery & equipment repair records, inspections, PM check sheets & programmed scheduling.


The various aspects of a good PM are quantitative technique as an aid to PM, network analysis, on load monitoring & off load monitoring. Adopting management techniques in PM involves method study & work measurements. Maintenance manuals & actual experience provides guidelines for effective inspection of equipment, so that corrective action can be made as required to prevent break downs.

 

 

2.0             Installation Drawings :

The various electrical engineering symbols as per ISI are furnished as annexure. The wiring diagrams & mechanical drawings shall be prepared so that they are simple to understand. Drawings are handy tools to install and maintain complicated equipments. The various clearances and tolerances, sequence of erection indicated should be strictly followed so that the equipments are installed, commissioned and maintained in an orderly way.

 

3.0           Electrical Installations : 

 

3.1      Instructions to be followed:

           The successful operation, maintenance &     long life of electrical equipments depends upon proper installations & use of correct starting, loading & shutting down procedures. The job of erecting & commissioning requires basic knowledge of its design, constructional details, auxiliaries, correct handling of components & alignment & operating procedures. The erections also need ability to judge the site conditions & eventualities which may arise in the day to day work. To ensure trouble free erection, commissioning & economical functioning of electrical equipments the following methods shall be adopted.

 

a)      Check on material receipt

b)      Storage precautions

c)      Transport of materials & equipments

d)     Pre installation checks

e)      Erection checks

As a contractor, for the successful completion of installation of any electrical equipments within the scheduled period requires man power planning, procurement of tools & plants, arrangement of stores & network planning.

  

3.2     Electrical Installations may be any one of the following

a)      Workshop, office & residential buildings

b)      Substation & power station

c)      Over head lines & under ground cable works

            Whatever may be the type of installation, broad principles are the same. The object is to ensure safety of work men & equipments under all circumstances. Certain precautions are to be taken such as., against shock, observation of safety rules, following safety of equipments, men & materials, following electrical safety measures in the machine laboratory, while handling, assembling & erection & commissioning.

 

3.3             Installation of Power Plant :

           The various equipment involved in the erection of a power plant are hydraulic equipments, electrical equipments, switching equipments, high tension systems, auxiliaries, miscellaneous equipments. The various types of installations are conventional, outdoor & semi out door, horizontal & underground. The equipments can be housed in super structures or on sub structures foundations depending upon the location. Certain facilities like water bypass, drainage, cable passages, trenches & ducts, location of transformer, circuit breakers, auxiliary equipments are to be provided besides cranes, mobile cranes and gantry cranes etc.,  other planning considerations to be looked upon are access roads, transport of equipments, movement of personnel and equipment during O & M.

           

 

The various stages of erection of a large capacity generator are:-

Embedded parts in first stage foundation, pier nose, D.T. liners, bottom cone, top cone, spiral segments

 

Pipes in second stage foundation, pivot ring & top cover assembly, guide vanes, runner & shaft assembly, regulating gear assembly, governor, gland assembly, TGB, air valves

 

Lower end bearing assembly, thrust bearing assembly, rotor & stator, top guide bearing, upper end bracket, exciter, brush & slip ring assembly, HP lubrication system etc.,

 

 

Alignment of the turbine & generator, centering of shaft, pre commission checks, balancing are the works involved in the erection. Before these activities certain factory tests & site tests including acceptance tests are also to be carried out to ensure that the equipments are correctly erected are commissioned and function properly.

 

4.0             Transmission & distribution :

 

4.1      Transmission system:

            Transmission lines are wires supported on poles and towers. When the transmission line has covered a large distance, it is then stepped down to 66 or 33 KV at the primary substation. From this substation, electrical energy is carried to different load centers through sub transmission lines.

 

4.2      Location of primary substation:

            Primary substations are located near a place which is near to the center of gravity of the load to be supplied to the substation. The sub transmission lines terminate at secondary sub stations which are located at the out skirts of a city or locality at 11 KV. Then this electrical energy at 11 KV is distributed to bulk & large consumers, domestic consumers at 240 V or 3 phases, 415 V through step down transformers. Engineers have developed symbols to draw the electrical power supply layout. Figures 1, 2 & 3 shows the flow diagrams of generation, transmission and distribution system

 

4.3      Installation of over head lines:

Planning of installation of over head lines comprises of materials & equipments conforming to relevant dimensions, standards & specifications. The over head lines must meet the requirement of IEA, REA, P & T department, road ways, local authorities etc. The installation should be carried out by authorized & trained personnel under the supervision of qualified engineers. The scope of installation consists of survey, material transport & handling, excavation, foundation works, erection of power & earth connectors, tensioning & sagging, safety precautions, testing & commissioning. The components to be installed are conductors, support poles & towers, insulators & miscellaneous components

 

Testing & commissioning of over head lines involves visual examination, cleaning & washing, continuity tests, insulation resistance tests etc.,

 

5.0             Service Lines

 

5.1   Consumer connection:

        A line that connects the installation of the consumer to a distributor is called service line. Service lines can be through bare conductor, over head lines & under ground cabling.

5.2    Ear thing: 

        Ear thing of these installations is essential to avoid the danger due to electrical shock & fire besides safety to the equipments. In electrical installations when a metal part of an electrical appliance comes in contact with live wire, it attains potential of the live wire. Any person touching the live material gets shock. So for safety it is essential to provide least resistance path. This will ensure high fault current to operate the circuit breaker or protective device to cut off the supply to the faulty equipment. So ear thing makes the safe operation of the equipment.

5.3    For every service main system, fuse boards are installed which divide into number

        of sub circuits. Fuses are normally re wire able type or HRC cartridge type. For

        every installation in a building, one main switch board shall be provided nearer to

        the service connection having one main switch and a number of MCCB’s & fuses.

 

6.0             Installation of underground cables & cable jointing :

 

a)     Care to be taken in handling the cable & jointing kits

b)     Skilled staff to be deployed

c)     Insulation resistance to be maintained within certain limits

d)     Safety Precautions to be observed in cable laying

e)     Pre commissioning site tests

f)      Cables can be laid in RCC trenches, pipes or ducts

g)     Cable schedules & routing to be planned

h)     Inspection methods to certify the acceptance tests at works, sample tests at works, type approval tests to be adopted

i)       Precautions to be taken in cable laying with respect to buried cables, maintaining clearances from buildings, communication cables, while crossing the roads & railway lines

 

7.0       Transformers

 

7.1              Stages involved in transformer installation are

a)      Dispatch of transformers

b)      Transporting of Transformers

c)      Inspection at works & site

d)     Storage & handling

e)      Civil works

f)       Hauling & placing the transformers

g)      Testing – type tests, routine tests & special Tests

h)      Commissioning tests

 

7.2              Typical tests to be carried out before commissioning are

a)      General Inspection

b)      Secondary injection

c)      Primary injection

d)     Ratio tests

e)      Tripping tests

f)       Calibration of buchholz relay

g)      Alarm circuit

h)      Fans & pumps

i)        Tap changers

j)        Phasing tests

k)      Insulation tests

l)        Check on oil level

m)    Load tests

n)      Conditioning of transformer oil

 

7.3       Following are the safety rules to be followed while transformer commissioning, starting, maintenance, inspection:      

a)      Disconnect the Transformer from supply

b)      Ground the line terminal & tank

c)      Disconnect both primary & secondary terminals

d)     Lock all the disconnected switches to open position

e)      Remove all fuses

f)       Relieve oil in the tank

g)      Clear all tools & personnel

h)      Always play safe to avoid accidents

i)        Ensure the transformer is fully de energized

j)        Before charging ensure that every thing is clear & there will be no accident on energizing

 

8.0      Sub station :

 

8.1     Selection & layout: Criteria for selection & layout of substations are:

a)      To use interchangeable transformers & spares

b)      To enable safe maintenance, inspection & commissioning

c)      Adequate clearances are provided between equipments & control auxiliaries.

d)     Provision to isolate the transformer & other equipments for scheduled maintenance works

e)      Provision to drain out oil from the transformer

f)       Protection of equipments against both electrical & mechanical faults

g)      Providing of surge arresters

h)      Providing of fire fighting equipments

 

8.2    Installation:

        Installation of a substation involves batteries, circuit breakers, transformers, indoor switch gear, out door circuit breakers, switch boards, ear thing, commissioning & testing of all the equipments for correct operations.

8.3 After installation, the circuit breakers, protective devices shall be subjected to

        Commissioning test to ensure that the assemblies are correctly made.  High accuracy

        is generally not expected in such tests.  The test facility available at site is also a

       deciding factor.  The following tests are normally carried out.

a)      Mechanical operation test

b)      Measurement of travel, simultaneously touching of contracts

c)      Measurement of insulation resistance, resistance between terminals of the poles.

d)     Pre commissioning checks.

e)      Open and Close operations.

f)       Checking the operation by energizing the manual operating signal.

g)      Checking the operation by energizing of relays.

 

8.4    For the installation of switch gear and bus bars, the following are to be

Observed:  Space selected should be such that sufficient space is available for easy operation and maintenance.  The layout plan is to be made and the work should be started in a methodical way.  Safety measures to be adopted.  The manuals provided by the suppliers to be followed strictly.

 

9.0     Industrial Installation  :

9.1   Industrial Installations involves the following.

a)      Proper installation of electrical equipments.

b)      Plans shall be laid for its testing and commissioning.

c)      Orders are to be placed in advance to meet the schedules.

d)     As soon as civil works and foundations are ready, the electrical machinery is placed.

e)      To carry out commissioning tests to ensure that these machines will be able perform satisfactorily, the duties assigned to them.

 

9.2   Equipments generally installed in an Industry are high voltage transformers,

             Protective equipments, various machines, storage batteries, DG Sets, Lifts, Cranes, Sub-Stations etc..

           

9.3   While installing the various equipments in an industry, the instruction

       Manuals provided by the manufacturers shall be strictly followed. The site testing of

       the equipments comprises of visual inspection, condition of mechanical parts, pre

      start test, check on protection and control circuits.

     

9.4  Commissioning of the machines involves

a)      Check of motor and motor starters.

b)      Check for unusual sounds.

c)      Check for electrical and mechanical faults.

d)     Temperature rise of the bearings.

e)      Overload trip test.

f)       Balancing.

 

10.0    Erection Conditions of the Contract

 

Apart from the technical conditions and  specifications of the various equipments installed, their testing, inspection and commissioning aspects, discussed in the earlier paragraphs, certain erection conditions of the contracts are also required to be followed for safe installation, commissioning and handing over of the equipments.  These erection conditions are discussed in detail under commercial aspects of electrical contracting.

 

 11.0    Maintenance of the electrical equipments:

 11.1   Any electrical installation either in a power station, sub station, industry is a continuously operating complex system, which requires close co- ordination of all the sectors. Any break down will give rise to major disturbances besides involving huge cost in rectification works. The reliable & economical operation of a power system depends on the proper operations & maintenance of the equipments in a systematic way & requires the following:

a)      Round the clock control of the operation & maintenance of the equipment

b)      Timely & well programmed routine repairs, over hauling, preventive maintenance, inspection & testing of the equipments

c)      Production support of the services like testing laboratories, repair shop, trained staff, stores having sufficient spares, insulating & lubricating materials needed for the everyday maintenance of the plant

d)     Good & reliable transport facility  

 

11.2     Keeping a keen watch for faults, timely remedial measures to rectify the same, minimize the damages can avoid emergencies during normal operating conditions. Electrical equipments do not suddenly develop fault. Faults like loose contact in switches, bus bar joints etc., and leakages in winding develop in to major faults. The insulated current carrying parts deteriorate with time & wear. The main causes for the failure of the equipments are accumulation of dirt & dust causing deterioration, defects in the manufactures, incorrect operation, and adverse atmosphere conditions.

11.3          Preventive maintenance should be carried out to identify the troubles & short comings noticed during daily operation, modernizing & improving of the equipment to give longer life, acting on the experience & feed back got from previous break downs.

11.4      The adequate planning of the repairs is done by drawing a defect list, indicating

           scope of work. The repair schedule showing the time schedule, various parts of

           equipments likely to be attended, list of materials required for the work, handling

           equipments & other facilities should be prepared to complete the work as per time

           Schedule.

11.5   Maintenance of a generating plant involves the following

a)      Daily inspection :- stator core, top & bottom guide bearing pads, thrust bearing, bearing oil, air coolers, collector, break & jack system, exciter, turbine guide bearing, cooling water systems, various auxiliaries, battery sets, etc.,

b)      Monthly inspection :- stator core, field winding, exciter, turbine guide bearing, cooling water system, oil system, auxiliaries, battery & battery charges, protective devices, etc.,

c)      Half yearly inspection :- stator core, windings, bearings, HP & LP systems, brake & jack system, poles, collector assembly, cooling water system, oil system, auxiliaries, battery & battery charges, protective devices, etc.,

d)     Annual inspection :- stator, field, brush gear & slip ring, exciter, bearings, air & oil coolers, turbine components,  auxiliaries, battery & battery charges, protective  devices, etc. ,shaft run outs, centering, etc.,

 

11.6    Maintenance of transmission lines

a)      Safety measures: - Before permitting maintenance works on line, the line should be switched off & DEAD circuit is identified & clearly marked. After isolation & ear thing at both ends, it must be earthed at the point of working to guard against induced voltages

b)      Routine Inspection: - Annual inspection is carried out before summer & winter. Patrolling is carried out after every lighting storms & high winds. Following points be clearly noted – broken strands of conductor, suspension clamps, broken guys & stay wire, broken or loose earth wire, cracked insulators, cross arms, tie wires, tension & suspension clamps, shackle pins, switch gear, transformer, cable seals, earth connection, loose nuts, accidental hazards like kite strings, damaged concrete foundations

c)      To reduce shut down time, hot line maintenance is also carried out using hot line tool kits

 

11.7    Maintenance of underground cables

            Requires minimum maintenance. The time schedule depends on the service experience & local conditions. Inspection involves visual, joint checking, condition of sheath, measuring insulation resistance, voltage tests, leakage current measurements.

 

11.8     The maintenance schedule of some major equipment are furnished in the enclosed annexure A to M. Annexure N furnishes the log books & history cards to be maintained during maintenance works 

 

12.0   Operation of electrical equipments

 

12.1      Introduction :

        Alert ness & sincerity of the shift personnel while on duty whether in a power house, sub station or industry ensures healthy run of the electrical equipments & improves reliability of power supply to the system / utilities / industry / consumers. They should be fully conversant with the location of various equipments, starting & stopping procedures, conditions of each equipment etc. They should initiate rectification measures immediately in case of any emergency. Operation manuals should be strictly followed. However individual awareness helps to a greater extent.

 

 

12.2       Activities involved

a)     Defining duties of each operating personnel

b)     Adopting suitable procedure for giving line clearances and returning of the same

c)     Detail checks to be exercised by the shift staff before taking charge

d)     Routine checks & operation of auxiliaries

e)     Precautions to be taken & checks to be made by the operating personnel before staring /closing of the equipments, synchronizing, normal stopping / opening etc.,

f)      Stopping the equipments / generating units on load

g)     Following instructions of changing over buses

h)     Operation of DC systems

i)       Operation of auxiliaries systems

j)      Operation of DC & AC distribution boards

k)    Operation of fire fighting equipments

l)       Operation of ventilation, air handling, AC plants, DG sets

m)  Knowledge of treatment for electric shock

n)     Knowledge of artificial respiration

o)     Procedure to issue line clearances in the prescribed formats & adopting safety measures

p)     Reporting any abnormalities of the performance of equipments    

  

13.0   Tools & Tackles:

For effective erection & maintenance of electrical equipments, the following tools & tackles are generally used.

1)      Power operated tools  

2)      Portable electric grinder

3)      Portable hand drill

4)      Nut runner

5)      Power wrench.

6)      Power scrapper

7)      Pneumatic scrapper

8)      Pulley, Hoist & Jacks

9)       Traveling Crane, Mobile Crane, Jib Crane.

10)  Ropes, Rope slings, Spanners, Screw drivers, Files, Wire Stripper

11)  Analog & Digital multimeter

12)  Pliers, Pocket Knife, Hammer, and Wooden saw, Chisels.

13)  Hand drill, Hacksaw, Auger bits, Rawl plug tool, Centre punch.

14)  Twist drill, Putty knife, Blow lamp, Plumb bob.

15)  Standard wire gauge, Lifting Tackle

In the assembly and erection of certain generator parts, special gadgets like 

a)      TURN CRADL (for turning the assembled core laminations to facilitate insertion of coils.

b)      Derricks (for hoisting the bridge girder of the EOT crane)

c)      Pipe Jacks (required for supporting and aligning the draft tube liner suctions).

d)     RCC stools (required for assembly of stator segments, Rotor rim building, Rotary valve etc).

e)      Heavy duty spanners

f)       Good workshop facility is also required with accurate, machines like Lathes, Milling Machines, Drilling Machines etc.,

g)      Trucks, Trailers, Lorries are also required.

 

Measuring instruments, high voltage testing equipments, DC heating equipments, laboratory arrangements for checking the protective devices, oil testing facilities etc., are also required. 